Skip to main content

Prefer Listening?

Hampton Council approves $45,000 storefront project payment

Hampton Council during their regular meeting Nov. 23

By
Mitch Williams

The Hampton City Council has approved a $45,103 payment to Tri-State Construction for work on the storefront stabilization project at 4 and 6 First Street Northwest.

Kalob Hays, with ISG, presented the payment request during Monday’s meeting. Hays told the council the project is now approximately 86% complete. The council approved the request as presented.

The council also approved a request from La Luz Centro Cultural to close the street directly in front of its building Saturday, Nov. 28, for a food truck. The closure will run from 11 a.m. to 6 p.m., with the food truck serving from noon to 6 p.m.

The next regular meeting was set for Thursday, Dec. 10, at 6 p.m.